Utility Relocation by Highway Contractor
Including utility work in a road contract improves coordination on road construction projects, especially when utility relocations cannot be accomplished before a road contractor begins work on a project. Road contractors can better control and coordinate the utility relocation schedule with road construction. There are several circumstances when it may be prudent to insert utility work in a road contract:
- To avoid extended property disturbance impacts if utility relocations occur in advance of road construction and the road contract letting is delayed. This is especially true for underground utility installations.
- When substantial clearing, roadway embankment construction, and/or roadway excavation must be completed prior to utility work.
- Right-of-way acquisition to accommodate utility relocation falls behind, which delays utility relocation work to the point that relocations cannot be substantially completed before road construction.
- The utility owner does not want to administer a separate contract for utility relocation and prefers that KYTC facilitate utility relocation through the road contract.
Many types of utilities can be incorporated into road contracts. Although water and sewer are the most common, the following table lists all facilities that may be included.
| Table 2 Recommended Mainline Taper Lengths | |
|---|---|
| Type of Taper | Taper Length |
| Most Common Installations |
|
| Limited Installations Usually limited to ducts and structures. |
|
| Occasional Installations Electric relocation has occasionally been inserted into road contracts, but usually only municipally owned utilities allow this. |
|
| Future Possibilities Although placement of communications facilities can be accomplished through a road contract, no utility is known to have allowed this. |
|
Use the flowchart below to determine if KYTC is responsible for reimbursing utility owners for relocation costs.
Use the flowchart below to determine if KYTC is responsible for reimbursing utility owners for relocation costs.
Side Note
Important considerations when including utility work in the highway contract are described below.
- Any agreement that includes utility work in a road contract must include language authorizing the contractor to perform the work. Use templates provided in KURTS for these agreements. They include the necessary language. See the HKP Article Utility Fiscal Documents for more information on agreement templates.
- KRS 177.035 Agreements (Municipal, Public Not for Profit Utilities)
- These agreements often include engineering, administration and/or inspection costs.
- If a project includes betterments, the utility company is responsible for paying that portion of the relocation costs.
- A Work-in-the-Highway Contract Betterment is used in this case. See Section UR-1104-4 (Work Type: Agreement Templates) in the Utilities and Rails Guidance Manual for more information.
- For more information on betterments, see the HKP Article Utility Betterments and Agreements.
- KRS 179.265 Agreements (Private For-Profit Utilities)
- For-profit utility companies must reimburse KYTC for their portion of the costs associated with relocations.
- The method for calculating the cost split will be detailed in the agreement.
- KYTC will bill a utility company for their portion as the project progresses.
- If betterment is included in the relocations, A Work-in-the-Highway Contract Betterment agreement is used.
- All betterment agreements must be negotiated prior to bidding of the road contract.
- Estimates shall use estimated unit costs.
- Language in betterment agreements should allow the Cabinet to invoice utility owners based on actual contract unit bid prices.
- Utility company administrative costs should be addressed in a separate agreement.
Any of the following personnel are qualified to develop utility relocation plans and specifications:
- Utility owner internal staff
- A consultant hired by the utility owner
- The roadway design consultant (through the road design contract)
- A KYTC-approved statewide utility consultant
- A combination of the above sources (e.g., a utility owner provided specs and a consultant prepared the plans)
The following items are included in road construction contracts:
- Plans
- Specifications
- Standard Drawings
- Preapproved contractors list provided by the utility owner (optional)
- Bid item descriptions and supplemental descriptions for special bid items
- General Utility Notes and Instructions Applicable to All Utility Work Made a Part of the Road Construction Contract (available on KYTC’s Utility Bid Items and Descriptions web page
Plans
The following requirements apply to all plans:
- Plans are on 24” x 36” plan sheets with standard KYTC borders that contain the sheet details and numbering across the bottom of each sheet
- All sheets are numbered in the bottom right block with the utility relocation numbering sequence (i.e., U1, U2, …).
- Text must be readable
- Final plan sheets are stamped and signed by a professional engineer
- Include a summary sheet as the first plan sheet
Specifications
The following requirements apply to all specifications:
- Specifications are on 8.5” x 11” sheets.
- Include all requirements related to materials, construction methods, and testing
Red Flag
The District Utility Agent reviews specifications to verify they contain no areas of conflicting information that do not conform to minimum Cabinet requirements for items such as trench compaction, restoration, and traffic control. The District Utility Agent makes edits on the specifications and returns them to the utility owner or utility consultant for correction and resubmission.
Standard Drawings
Plan sheets included in the utility plan set may contain utility construction standard drawings. These drawings may also be placed on 8.5“ x 11” sheets at the end of specifications.
Red Flag
The District Utility Agent reviews standard drawings showing permanent trench compaction and pavement restoration to verify compliance with Cabinet minimum requirements. The agent makes edits on the standard drawings and returns them to the utility owner or utility consultant for correction and resubmission.
Pre-Approved Contractors List
A utility owner may submit a list that includes at least three contractors who are preapproved by the utility to perform utility construction. Utility owners, however, are not required to provide this list.
Bid Items and Descriptions
Unit bid items and descriptions are used to quantify utility relocation work. Several important issues related to bid items and descriptions must be considered.
- Use standard KYTC Utility Bid Items Descriptions.
- Bid Item codes that correspond to these descriptions are compiled in the Bid Items spreadsheet maintained by the Division of Construction.
- Utility items are sorted or filtered by their Item Type (UTLN).
- Utility items are also organized Item Numbers assigned to each utility type (e.g., water, sewer, gas) as noted in the header of the spreadsheet.
- The road contract must include a complete list of bid items and descriptions for each type of utility construction. This list must also be included in submittals for bidding.
- Utility designs occasionally require use of a unique bid item not included among KYTC’s standard utility bid items and descriptions. When this happens, use the Special bid items in the list of standard KYTC bid items. These are available for multiple areas. Using them avoids the need to create new one-time or limited use bid items.
- The word special must be included in the bid item name, and a supplemental bid item description must be developed and included in the proposal.
- Bid items and descriptions were developed to reduce the number of pay items and establish consistent measurement methods and payment methods across all utility types. Examples of this are described below.
- Pipe bid item descriptions include all common fittings as incidental. KYTC inspectors do not need to count individual fittings for new main installations. Only major fittings (e.g., new valves and assemblies) are paid individually.
- Service laterals are paid as long side or short side and include connection fittings. No linear measurement of service laterals is needed.
- Fire hydrants are paid as assemblies and include isolating valves and main tees.
- Water meters are paid as assemblies including meter, box and connecting fittings.
- INST bid items apply to items where the utility owner may want to provide the major components and have the road contractor or subcontractor perform the intallation.
- There are no standard utility bid items for plugging and safeloading of abandoned pipes. Standard roadway bid items must be used for these activities.
- Utility bid items for pipe plugs and caps are only for use on existing facilities that will remain in service. They should not be used on pipes slated for abandonment.
- These items should not be paid separately on new installations. They are installed on new main installations and considered incidental (like other new fittings on new mains).
General Utility Notes and Instructions
A link to the General Utility Notes and Instructions Applicable to All Utility Work Made a Part of the Road Construction Contract is available on KYTC’s Utility Bid Items and Descriptions web page. This note is inserted into a proposal by the District Utility Agent. It covers several facets of the contract:
- Specifies what documents and notes take precedence if contract document conflicts are found (a) in plans and/or specifications supplied by a utility owner or consultant or (b) in any other contract documents.
- Protection of existing utilities
- Identifies all utility owners requiring the use of prequalified contractors to perform work on their facilities.
- Procedure to follow when a utility does not have a prequalified contractor requirement
- Contract administration of utility work
- Procedure for utility submittals and correspondence
- Defines terms and responsibilities of the Engineer, Inspector, and Resident Project Representative (positions utility plans and specifications may refer to)
- Requirements for notifying a utility owner of the start and suspension of utility work
- Requirements for utility shutdowns
- Customer service lines and lateral abandonments
- Interpretation of utility installation stations and distances as shown on plans
- Restoration of utility work areas
- Materials to be supplied by the utility owner
- Security of materials supplied by the utility owner
A construction cost estimate of required utility relocations must be prepared and submitted with the bidding documents described above. Important features of this estimate include:
- Bid items and quantities
- These should match those on the plan summary sheet.
- Type of utility, utility owner, project item number, and date of the estimate was generated
- Columns in the estimate should include:
- Item Code
- Item Description
- Quantity
- Unit Price
- Item Total
- Grand total
- Separate estimates for each utility type
Sources of unit prices include KYTC average prices from past years, recent local highway projects, and recent projects bid by the utility owner. If necessary, estimators can interpolate prices using information form these sources. Unit prices from past state contracts and utility owner contracts vary widely. Inflation and material availability also influence current prices.
Red Flag
|
District Utility staff must review all prices (regardless of source) to determine if they align with current cost expectations. |
Once the District Utility Agent gathers plans and documents and they are ready for submittal, the agent uploads them to Project Wise.
All plan and document file uploads must be in .pdf format. File names must start with the District number, which is followed by the item number, type of utility, and document type. For example:
- 06-444.00 Gas Estimate.pdf
- 06 is the District, 444 is the item number, Gas is the utility type, and Estimate is the document type.
- 06-444.00 San Sewer Plan.pdf
- 06 is the District, 444 is the item number, San Sewer (i.e., sanitary sewer) is the utility type, and Plan is the document type.
If a road contact includes multiple utility owners relocating the same type of facility (e.g., gas, water), file names may be expanded to include a utility owner’s initials. For instance:
- 06-444.00 NKWD Water Spec.pdf
- 06-444.00 BCWD Water Plan.pdf
- In these examples, NKWD and BCWD are the utility owner initials.
Upload documents to the ProjectWise folder specified in the table below.
| Document | ProjectWise Folder |
|---|---|
|
Item No./Milestones & Submittals/Contract Plans and Proposal/Contract Plan Set/Utilities |
|
Item No./Milestones & Submittals/Contract Plans and Proposal/Proposal |
|
Item No./Milestones & Submittals/Contract Plans and Proposal/Miscellaneous |
A preconstruction conference is a formal meeting during which KYTC representatives, the contractor, and other interested parties review construction details, proposed schedules, and other project details. At this conference, the prime contractor will identify who is to perform utility work (prime contractor or one of the sub-contractors).
Other important items discussed at the preconstruction conference include:
- The entity performing construction (i.e., prime contractor or a subcontractor)
- Check this information against the preapproved contractors list if applicable
- Contact information for the utility owner, contractor, and Section Engineer’s office
- Tentative schedule of utility relocations
- An onsite review (if necessary) should be held before utility work begins.
KYTC’s Section Engineer is responsible for contract administration. As such, they resolve all issues related to contract administration and utility inspection.
The contractor should address the following submittals to the KYTC Section Engineer:
- Material certifications
- Catalogue cuts
- Shop drawings
- Utility construction schedule
- All other submittals required by specifications
To expedite reviews, the contractor may send copies of submittals to the utility owner at the same time they send them to the KYTC Section Engineer.
The utility owner should review all submittals. A utility owner must submit review comments and approvals of submitted items to the KYTC Section Engineer. In turn, the Section Engineer will communicate results to the contractor.
All field inspections must be conducted jointly by KYTC inspectors and the utility owner or consultant inspectors. Field inspection responsibilities are listed in the table below.
| Responsible Party | Inspection Duties |
|---|---|
| Utility owner inspector or utility owner consultant |
|
| KYTC Section Engineer Office staff |
|
If a utility owner or consultant inspector observes a construction-related issue that cannot be resolved through direct discussions with the contractor, they should report it to KYTC’s Section Engineer and field inspector for resolution.
The KYTC Section Engineer should confirm that utility installation was performed to the satisfaction of the utility owner before the Cabinet makes final payment to the contractor. Other conditions that must be met are listed below.
- All work must be completed to the satisfaction of the utility owner
- This releases KYTC from future liability.
- Unsatisfactory work must be corrected
- The District Utility Agent and Section Engineer must coordinate betterments.
- The District Utility Agent should confirm final pay quantities and the portion of the betterment construction that is billable to the utility company.
- The District Utility Agent must coordinate payments with Central Office Division of Accounts, which in turn invoices the utility owner.
- During this process, the following information must be submitted to the Division of Accounts and copied to the Utility Area Coordinator:
- Battement agreement
- Utility name, contact, address, and telephone number
- Partial billing of betterment construction is allowed.
- Once the Division of Accounts receives all final payments from the utility owner, the betterment agreement may be closed.
The District Utility Agent may need to contact the Central Office Division of Accounts to confirm collection of all billed amounts for closure of a betterment agreement.